Central Railway (CR) launched a 30.5-meter span open web girder weighing 100 MT for a rail fly over on Bhadli-Jalgaon 4th line (part of Jalgaon-Bhusaval 24km – 4th line project) on January 12, 2022.

The main girder was launched by end-launching method with launching nose of 21-meter span attached to the main girder.

Five temporary support trestles were erected for movement of girder assembly. The track over the girder is pre-linked with H-beam sleepers. The launching of the girder completed by operating a four hour block on the section.