CR: Byculla Station’s Kalyan End FOB Closed for Repairs Temporarily

Temporary Closure of Kalyan end old Foot over Bridge at Byculla Station.

The Kalyan end foot over bride over two span connecting Platform No. 1, 2, and 3 and Platform No.4 at Byculla station will be closed for repair work from 07.02.2020 to 06.03.2020 in phase manner as under.

Phase-I :- The span from platform No.4 to platform No.3 will be closed for repair.  The other portion from platform No.2 to platform No.1 will be kept open for movement of passengers.

Phase-II :- The repairing work will be carried out from platform No.2 to platform No. 1 with staircase and will be closed while repaired portion from platform No.3 to platform No.4 will be open for use of passengers.  During this period public can use Mumbai (South) end foot over bridge.