Electrification: Revised 2019-20 Targets for CR, All of Pune – Miraj – Kolhapur route to be completed this year

The Railway Board has reviewed Electrification targets and has come up with revised quarterly commissioning targets for every zone.

RB had earlier set a steep target of over ten thousand kilometres of route to be electrified in 2019-20 across IR.

With the revision of targets, new sections added to this year’s schedule. These include Jasai – Jawaharlal Nehru Port Trust, Miraj – Kolhapur and Kirloskarwadi – Miraj. The total route km to be electrified on CR in 2019-20 has now increased from 722 km to 859 km.

Below are the revised targets and expected timelines for commissioning of electrification for Central Railway:

SectionElectrification Target for 2019-20Zonal JurisdictionExecuting AgencyTarget QuarterRemarks
Wani – Pimpalkhutti66CRRVNLQ1 
Solapur – Boroti – Gulbarga109CRRVNLQ3 – Q4Q3: Solapur Boroti, Q4: Boroti – Gulbarga
Bhigwan – Wadshinge – Solapur160CRRVNLQ3 – Q4Q3: Bhigwan – Wadshinge, Q4: Wadshinge – Solapur
Miraj – Kurduwadi180CRCOREQ2Another entry added with revised distance
Satara – Kirloskarwadi94CRPGCILQ3 
Shindwane – Satara113CRPGCILQ2 
Kirloskarwadi – Miraj39CRPGCILQ3Added in Revised Target
Miraj – Kolhapur48CRPGCILQ1Added in Revised Target
Pune – Shindawane32CRPGCILQ1Added in Revised Target
Miraj – Kurduwadi (Additional Distance in Revision)9CRCOREQ2Revised Distance from 180 to 189 km
Jasai – Jawaharlal Nehru Port Trust (Mumbai)9CRCRQ3Added in Revised Target

Related Posts

This Post Has One Comment

  1. What is the use? The targets were never intended to be achieved or laggards ever punished. Targets are meant only for postponement and revision afterwards. Nobody is bothered in central railway at least.

Got something to say? Post a comment!