Indian Railways (IR) is likely to complete 56 rail projects by the end of FY22 ( March 2022) according to the Railway Board. All these projects are under various stages of completion.
The projects are as follows:-
S.No. | Name of Project | Length of Project (Km) | Month/Year of commissioning |
1 | Hansdiha-Godda New Line | 32 | Feb-21 |
2 | Omalur-Metturdam Patch Doubling | 29 | Feb-21 |
3 | Netravati-Mangalore | 2 | Feb. 21 |
4 | Nirmali – Saraigarh New line including Kosi Bridge | 22 | Mar-21 |
5 | Ahmedabad-Botad | 170 | Mar-21 |
6 | Pilibhit-Shahjahanpur Gauge Conversion | 83 | Mar-21 |
7 | Utretia – Raebarelli | 66 | Mar-21 |
8 | Ghazipur-Aunrihar | 40 | Mar-21 |
9 | Bhusawal-Jalgaon 3rd line | 24 | Mar-21 |
10 | Ambari-Falkata doubling | 38 | Mar-21 |
11 | Ambalapuzha-Haripad | 18 | Mar-21 |
12 | Tambram-Chengalpattu Gauge Conversion | 30 | Mar-21 |
13 | Ajmer-Bangurgram Doubling | 47 | Mar-21 |
14 | New Mynaguri-Gumanihat | 52 | Apr-21 |
15 | Jayanagar – Bijalpura | 52 | May-21 |
16 | Dhasa – Jetalsar GC | 104 | May-21 |
17 | Bangurgram-Guriya Patch DL | 47 | May-21 |
18 | Hajipur-Bachwara doubling | 72 | May-21 |
19 | Kankanadi-Panambur | 19 | May-21 |
20 | Raibarelli-Amethi doubling | 60 | May-21 |
21 | Pendra Road-Anuppur – 3rd line | 50 | May-21 |
22 | Daund-Gulburga doubling | 225 | Jun-21 |
23 | Khurda Rd-Bararng | 32 | Jun-21 |
24 | Katereah-Kursela patch doubling | 7 | Jun-21 |
25 | Bandel Boinchi 3rd line | 31 | Jun-21 |
26 | Mathura-Palwal 4th line | 80 | Jun-21 |
27 | Jallandhar-Pathankot-Jammu Tawi doubling | 209 | Jun-21 |
28 | Manoharpur-Bondamunda 3rd line | 30 | Jun-21 |
29 | Kharagpur-Narayanagarh 3rd line | 24 | Jun-21 |
30 | Arsikere-Tumkur doubling | 96 | June 21 |
31 | Raibareilly-Amethi Doubling | 60 | Jun-21 |
32 | Secunderabad-Mehboobnagar doubling | 85 | Jun-21 |
33 | Yelahanka-Penukonda doubling | 123 | Jun-21 |
34 | Bhadrachalam Road-Sattupalli | 54 | Jun-21 |
35 | Vijayawada-Gudiwada-Bhimavaram-Narsapur, Gudiwada-Machlipatnam | 221 | Jul-21 |
36 | Madurai – Bodinayakkanaur gauge Conversion | 90 | Sep-21 |
37 | Ahmedabad-Mehsana Gauge conversion | 69 | Oct. 21 |
38 | Digaru-Hojai doubling | 102 | Oct. 21 |
39 | Dausa-Gangapur City New Line | 93 | Nov. 21 |
40 | Sambalpur-Talcher doubling | 168 | Dec-21 |
41 | Sambalpur-Titlagarh doubling | 106 | Dec-21 |
42 | Raipur-Titlagarh | 203 | Dec-21 |
43 | Banspani-Daitari-Tomka-Jakhapura doubling | 164 | Dec-21 |
44 | Dankuni-Chandanpur 4th line | 25 | Dec-21 |
45 | Boinchi Shaktigarh 3rd line | 26 | Dec-21 |
46 | Bhimsen-Jhansi doubling | 206 | Dec-21 |
47 | Kurruppanthara-Chingavanam doubling | 27 | Dec. 21 |
48 | Bina-Kota doubling | 283 | Dec. 21 |
49 | Viramgam-Samakhyali doubling | 182 | Dec. 21 |
50 | Ayodhya- Varanasi – Railway Electrification | 188 | 28-Feb-22 |
51 | Guwahati-Lumding- – Railway Electrification | 180 | 28-Feb-22 |
52 | Mansi-Saharsa, incl. Saharsa-DauramMadhepura-Purnia& MM Banmakhi- Bihariganj Gauge Conversion | 169 | 31-Mar-22 |
53 | Palanpur-Makarpura section (WDFC) | 308 | 31-Mar-22 |
54 | Rewari-Dadri section (WDFC) | 127 | 31-Mar-22 |
55 | Palanpur -Kandla port-Mundra port-Bhuj- Railway Electrification | 475 | 31-Mar-22 |
56 | Hospet-Hubli-Vasco – Railway Electrification | 341 | 31-Mar-22 |