More DFC Delays Spur Ministry, Railway Officials Into Action

With full commissioning of the Dedicated Freight Corridor pushed back further to June 2022, Indian Railways officials have started going after chronic reasons for delays.

Land acquisition problems have caused significant delays to commissioning of parts of the DFC. 200 hectares of land was still pending award by the end of July 2020 on the Eastern Dedicated Freight Corridor. On the PPP stretch of the EDFC between Sonnagar and Dankuni, 25% of award of land notified is pending.

In order to cut down on red tape and push the process through, Railway Minister Piyush Goyal recently held a meeting with state government Chief Secretaries. Letters were also written to Chief Ministers of Uttar Pradesh, West Bengal, Bihar, Punjab, Haryana, Gujarat and Maharashtra by Goyal, according to a statement released by the Ministry.

Review meetings are also taking place with various stakeholders, including contractors involved in the execution of the project, the statement said.

Dedicated Freight Corridor Commissioning Status

First announced in 2005, the 3,660-kilometre project has moved forward at a glacial pace over the past one and a half decades. With the first contracts awarded, work finally began on the ground in 2013.

Parts of the corridor have been commissioned. A 306 km stretch of the Western Dedicated Freight Corridor between Rewari-Madar has been commissioned. Over 580 trains have already run on this stretch so far.

Sign up for RailPost’s Telegram Group to Discuss Railways! Go here: http://telegram.me/RailPostGroup

Stay connected to RailPost! Follow us on Twitter, Facebook, Instagram or Linkedin. Or join our Telegram channel. Choose your preferred options here: www.railpost.in/connect/

On the Eastern Dedicated Freight Corridor, the 194 km stretch between Khurja-Bhadani has been commissioned. Over 1,270 trains have been operated on this section according to a July 2020 DFCCIL status report of the project.

Section-wise Dedicated Freight Corridor Commissioning Timeline As of August 2020

RouteSection / PackageLength (kilomtres)StatusTimeline (As of August 2020)
1Western DFCDadri – Rewari127WIPMarch 2022
2Western DFCRewari Palanpur (Rewari – Madar)306Complete
3Western DFCRewari Palanpur (Madar- Marwar)143WIPDecember 2020
4Western DFCRewari Palanpur (Marwar- Palanpur)204WIPMarch 2021
5Western DFCPalanpur – Makarpura289WIPMarch 2022
6Western DFCMakarpura – Sachin135WIPJune 2022
7Western DFCSachin – Vaitarna186WIPJune 2022
8Western DFCVaitarna – JNPT101WIPJune 2022
9Eastern DFCLudhiana – Pilkhani179WIPJune 2022
10Eastern DFCPilkhani – Khurja222WIPJune 2022
11Eastern DFCKhurja – Dadri46WIPJune 2021
12Eastern DFCKhurja – Bhaupur (Khurja-Bhadan)194Complete
13Eastern DFCKhurja – Bhaupur (Bhadan-Bhaupur)157WIPOctober 2020
14Eastern DFCBhaupur – Mughalsarai402WIPJune 2022
15Eastern DFCDurgawati – Sasaram56Complete
16Eastern DFCMughalsarai-Sonnagar (Balance)81WIPJune 2021