In line with plans and fund allocations set out in budgets for 2018-19 and 2019-20, targets have recently been set out for various zones and executing agencies for the financial year 2019 – 20.
The hike in targets is substantial in several cases, despite below par achievement of targets set the previous financial year.
Details of zone-wise targets for zones and executing agencies are provided in four tables below. Separate tables with breakup for New Line, Gauge Conversion and Doubling/Tripling works can be viewed below the table with overall totals.
Total New Line, Doubling, Gauge Conversion Targets for the Financial Year 2019-20
Zone | Spill-Over from 2018-19 (in kilometres) | Target for 2019-20 (in kilometres) | Total Target 2019-20 (in kilometres) |
Central Railway (CR) | 274 | 394 | 668 |
Eastern Railway (ER) | 151 | 96 | 248 |
East Central Railway (ECR) | 475 | 293 | 768 |
East Coast Railway (ECoR) | 250 | 284 | 534 |
Northern Railway (NR) | 164 | 101 | 265 |
North Central Railway (NCR) | 99 | 210 | 309 |
North Western Railway (NWR) | 364 | 109 | 474 |
North Eastern Railway (NER) | 190 | 241 | 430 |
North East Frontier Railway (NFR) | 176 | 208 | 385 |
Souther Railway (SR) | 153 | 108 | 261 |
South Central Railway (SCR) | 335 | 271 | 606 |
South Eastern Railway (SER) | 114 | 99 | 213 |
South East Central Railway (SECR) | 214 | 279 | 493 |
South Western Railway (SWR) | 142 | 340 | 482 |
West Central Railway (WCR) | 151 | 123 | 274 |
Western Railway WR | 291 | 268 | 559 |
Total of Zonal Railway Targets | 3,543 | 3,425 | 6,968 |
Rail Vikas Nigam Ltd | 704 | 80 | 784 |
Dedicated Freight Corridor Corporation of India Ltd | 0 | 1,000 | 1,000 |
IRCON International | 183 | 273 | 456 |
RITES | 58 | 52 | 109 |
Total New Line Target | 4,488 | 4,829 | 9,318 |
Detailed break-up as follows :
New Line Targets for the Financial Year 2019-20
Zone | Spill-Over from 2018-19 (in kilometres) | Target for 2019-20 (in kilometres) | Total Target 2019-20 (in kilometres) |
Central Railway (CR) | 134 | 69 | 203 |
Eastern Railway (ER) | 27 | 17 | 44 |
East Central Railway (ECR) | 236 | 29 | 265 |
East Coast Railway (ECoR) | 45 | 45 | |
Northern Railway (NR) | 0 | 61 | 61 |
North Central Railway (NCR) | 0 | 0 | |
North Western Railway (NWR) | 116 | 116 | |
North Eastern Railway (NER) | 0 | 0 | |
North East Frontier Railway (NFR) | 100 | 75 | 176 |
Souther Railway (SR) | 18 | 18 | |
South Central Railway (SCR) | 94 | 90 | 185 |
South Eastern Railway (SER) | 0 | 0 | |
South East Central Railway (SECR) | 0 | 0 | |
South Western Railway (SWR) | 28 | 79 | 107 |
West Central Railway (WCR) | 60 | 60 | 120 |
Western Railway WR | 35 | 16 | 51 |
Total of Zonal Railway Targets | 894 | 496 | 1,390 |
Rail Vikas Nigam Ltd | 157 | 80 | 237 |
Dedicated Freight Corridor Corporation of India Ltd | 0 | 0 | |
IRCON International | 57 | 88 | 145 |
RITES | 0 | 0 | |
Total New Line Target | 1,109 | 664 | 1,772 |
Doubling/Tripling Targets for the Financial Year 2019-20
Zone | Spill-Over from 2018-19 (in kilometres) | Target for 2019-20 (in kilometres) | Total Target 2019-20 (in kilometres) |
Central Railway (CR) | 140 | 326 | 465 |
Eastern Railway (ER) | 124 | 80 | 204 |
East Central Railway (ECR) | 129 | 264 | 393 |
East Coast Railway (ECoR) | 205 | 284 | 489 |
Northern Railway (NR) | 164 | 40 | 204 |
North Central Railway (NCR) | 99 | 210 | 309 |
North Western Railway (NWR) | 72 | 27 | 99 |
North Eastern Railway (NER) | 152 | 160 | 312 |
North East Frontier Railway (NFR) | 76 | 133 | 209 |
Souther Railway (SR) | 61 | 55 | 116 |
South Central Railway (SCR) | 197 | 180 | 378 |
South Eastern Railway (SER) | 114 | 99 | 213 |
South East Central Railway (SECR) | 73 | 173 | 246 |
South Western Railway (SWR) | 114 | 261 | 375 |
West Central Railway (WCR) | 91 | 63 | 154 |
Western Railway WR | 122 | 115 | 237 |
Total of Zonal Railway Targets | 1,933 | 2,470 | 4,403 |
Rail Vikas Nigam Ltd | 382 | 382 | |
Dedicated Freight Corridor Corporation of India Ltd | 0 | 1,000 | 1,000 |
IRCON International | 126 | 168 | 294 |
RITES | 58 | 52 | 109 |
Total New Line Target | 2,499 | 3,690 | 6,189 |
Gauge Conversion Targets for financial year 2019-20
Zone | Spill-Over from 2018-19 (in kilometres) | Target for 2019-20 (in kilometres) | Total Target 2019-20 (in kilometres) |
Central Railway (CR) | 0 | 0 | |
Eastern Railway (ER) | 0 | 0 | |
East Central Railway (ECR) | 110 | 110 | |
East Coast Railway (ECoR) | 0 | 0 | |
Northern Railway (NR) | 0 | 0 | |
North Central Railway (NCR) | 0 | 0 | |
North Western Railway (NWR) | 177 | 82 | 259 |
North Eastern Railway (NER) | 38 | 80 | 118 |
North East Frontier Railway (NFR) | 0 | 0 | |
Souther Railway (SR) | 74 | 53 | 127 |
South Central Railway (SCR) | 43 | 43 | |
South Eastern Railway (SER) | 0 | 0 | |
South East Central Railway (SECR) | 141 | 106 | 247 |
South Western Railway (SWR) | 0 | 0 | |
West Central Railway (WCR) | 0 | 0 | |
Western Railway WR | 134 | 138 | 271 |
Total of Zonal Railway Targets | 716 | 459 | 1,175 |
Rail Vikas Nigam Ltd | 165 | 165 | |
Dedicated Freight Corridor Corporation of India Ltd | 0 | 0 | |
IRCON International | 0 | 17 | 17 |
RITES | 0 | 0 | |
Total New Line Target | 881 | 476 | 1,357 |
Work to be executed by agencies like RVNL, IRCON and RITES is spread across various zonal jurisdictions, but not counted under the zonal execution target.