South Coast Railway to commence earliest by February 1, 2020

DPR reveals more details on what is likely to be the final shape of the newest zone on Indian Railways

The newly created railway zone South Coast Railway (SCoR) is likely to commence operations earliest by February 2020. This is according to the detailed project report (DPR) submitted to the railway board.

The new zone will have three divisions- Vijayawada (BZA), Guntur (GNT) and Guntakal (GTL). The Waltair (WAT) division of ECoR will be split into 2 parts. The SCoR portion of WAT division will be merged with BZA division while the ECoR portion will go to the Khurda Road division (KUR) and the newly created Rayagada (RGDA) division. 

SCoR will be under Commissioner of Railway Safety South Central circle Secunderabad.

SCoR
Division Route km
BZA 1414
GTL 1452
GNT 630
Total 3496

Bifurcation of WAT division

Of the existing 1106 route kilometres in WAT division, 115 will go to KUR division of ECoR, 541 route km to RGDA division of ECoR and the remaining 450 route km merged with BZA divison of SCoR. This will be as follows:

1.       Koraput (KRPU)-Singapur Road (SPRD) -164 km to RGDA division

2.      Kottavalasa (KTV)-Araku (ARK incl) – 106 km under SCoR while ARK (excl)-Kirandul (KRDL) -360 km under ECoR RGDA division

3.      Vizianagaram (VZM)- SPRD section – VZM-Kuneru incl (KNRT) 102 km and Bobbili(VBL)- Salur (SALR) 17-km branch line to SCoR. KNRT excl- SPRD -37 km to RGDA division

4.      New line between Theruvali (THV) and Gunupur (GNPR) – 79 km long to be under RGDA. This line connects VZM- PSA main line to VZM-R line. The PSA -Naupada (NWP) 25 km main line and the NWP -GNPR 90 km branch line will be under ECoR.

5.      SCoR’s BZA division will get Duvvada (DVD)-VSKP-VZP-NWP main line besides all branch lines in and around VSKP: Duvvada (DVD) – Jaggayyapalem (JGPM), DVD-Vadlapudi (VDPD), VSKP Steel Plant- VDPD- Simhachalam North (SCMN) and SCMN -DVD bypass line.

Interchange points between SCoR and ECoR

The new zonal inter-change points proposed in DPR are as follows:

Section Interchange Point Between divisions
VSKP-PSA mainline Naupada under KUR division, ECoR BZA-KUR
KTV-KRDL line Araku under BZA division, SCoR BZA and RGDA
R – VZM line KNRT under BZA Divison, SCoR BZA and RGDA

Headquarter staff: order of priority

The order of priority for staffing will be: First, WAT division employees will be given an option to be posted at SCoR headquarters first, next in line will be SCR staff; then ECoR staff and finally employees from other zones.

Construction/ Projects Organisation

 The construction organization and S&T (projects) of SCoR will also be split according to project works being executed as per the re-drawn zonal jurisdiction. 89 out of 182 SCR projects will go to SCoR. Of this, one doubling tripling /project is present in both these zones.

How it will be done

Once the DPR is approved, the earliest date of commencement of SCoR will be Feb 1 2020.  This date could shift to April 1, 2020, in sync with the financial year. SCoR zonal headquarters will have a floor space of 23000 square metres.

SCoR set up cost heads in Rs crore
Headquarters construction 111.02
Officers’ quarters construction 69.76
40 new SG/JAG posts at HQ 6.3
Re-do WAT division office 4.8
Re-do operational control boards at BZA 1.3
Total 193.18

A multi-disciplinary team of officers under the officer on special duty (OSD) SCoR will implement the new zone creation. An ADRM will be posted at VSKP under the BZA division control to ensure smooth rail operations.   

During the transition period- a central control will be set up at VSKP, WAT division control will be redistributed between BZA and RGDA/KUR and material management contracts during transition period will continue till the new material department is set up and they start working on new contracts.

SCoR at a glance
Route kilometres3496
Track kilometres5437
Freight loading FY1986.7 million tonnes
Originating passengers FY19192.5 million
Sanctioned staff strength65800
Staff on rolls54500
Freight handling portsVisakhapatnam, Gangavaram, Krishnapatnam and Kakinada
Major stationsVSKP, BZA, TPTY
Loco sheds3 electric(BZA, GTL WAT) and 4 diesel ( WAT, BZA, GY and GTL)
WorkshopsCarriage workshop TPTY, Wagon workshop Rayanapadu ( RYP) and new wagon workshop at Vadlapudi near VSKP
Major freight examination yardsWAT, BZA, COA and GY
Coaching depotsWAT, VSKP, TPTY, NS, MTM, BZA and Kakinada (COA)
Track Machine WorkshopCentral POH at RYP
MEMU workshopRajahmundry (RJY)

Related Posts

Got something to say? Post a comment!