Central Organization for Railway Electrification (CORE) plans to complete 6,234 route km of electrification in FY 19-20. CORE is tasked with electrification of 22,800 route km of railway lines across… Read more
In this part, we take a look at IR’s infrastructure enhancement plans in its roadmap for the future. Read more
Several key issues on Policy and Infra that continue to bog down IR are likely to be on the new railway minister's plate. Read more
The dedicated freight corridor (DFC) connecting Ludhiana in Punjab to Dankuni near Kolkata and Jawaharlal Nehru Port Trust (JNPT) near Mumbai is likely to fully functional by March 2020 Read more
Revised timelines and targets have been set out for the three zones in Southern India for the financial year 2019-20 by the Railway Board. Read more
Central Railway gets revised electrification targets, up from 722 km to 859 km in 2019-20 Read more
The Indian Railways has set itself a target of 8.6 billion originating passengers in the financial year 2019-20 Read more
IR targets a 5% increase in freight loading for the financial year 2019-20 at 1285 million tonnes. Read more
WR has been set a target of 559 km of commissioning of New Line, Doubling and Gauge Conversion work in the financial year 2019-20, according to sources. Read more
East Coast Railway recently submitted fresh timelines for completion of works that were to be completed within 2018-19 to the board. Read more