WR has been set a target of 559 km of commissioning of New Line, Doubling and Gauge Conversion work in the financial year 2019-20, according to sources.
The Mumbai based zone was only able to achieve 45% of its annual target for the year 18-19. Despite the low actual figures, WR ranks among the best when compared to other zones such as CR with a mere 15% of the target achieved, and WCR with an even lower tally of 10%.
Below is the list of works that were not completed in the previous financial year, and are now part of spillover targets to be executed in 2019-20. Timelines for completion, as currently planned, are also provided.
Name of Project | Section | Expected Commissioning By | Type of Project | Length (in km) |
Dahod – Indore via Sardarpur, Jhabua & Dhar New line (204.76 Km) | Dahod-Katwara | February 2020 | New Line | 11.40 |
Chotta Udepur – Dhar | Alirajpur- Jobat | December 2019 | New Line | 24.00 |
Mahesana-Taranga Hill | Mahesana-Vadnagar | June 2019 | Gauge Conversion | 33.00 |
Dabhoi-Chandod – Gauge conversion with extension upto Kevadiya (49.75 km) | Dabhoi-Chandod | December 2019 | Gauge Conversion | 18.00 |
Ahmedabad-Mehsana (68.78 Kms.) | Sabarmati-Kalol | June 2019 | Gauge Conversion | 20.64 |
Ratlam-Mhow-Khandwa-Akola GC(472.60 Kms.) – (298.60 Kms. in WR) | Mathela-Attar –Nimarkher | April – June 2019 | Gauge Conversion | 50.70 |
Ratlam-Mhow-Khandwa-Akola GC(472.60 Kms.) – (298.60 Kms. in WR) | Sanawad-Nimarkheri | December 2019 | Gauge Conversion | 11.30 |
Chittor-Nimach Doubling (55.73 Km) | Shambhupura to Nimbaheda | October 2019 | Doubling | 14.90 |
Vatva-Ahmedabad – 3rd line with automatic signalling (7.50 Kms.) | Vatva – Ahmedabad | June 2019 | Tripling | 7.50 |
Viramgam-Samakhiyali ( DL) (182.23 Km) | Sadla-Bajana-Jatpipli | June 2019 | Doubling | 17.25 |
Viramgam-Samakhiyali ( DL) (182.23 Km) | Sukhpur-Halvad-Khakhrechi | September 2019 | Doubling | 33.95 |
Viramgam-Samakhiyali ( DL) (182.23 Km) | Khakhrechi-Wadharva | November 2019 | Doubling | 8.38 |
Doubling of Indore-Ujjain ( 80 Km) | Ujjain-Karchha | October 2019 | Doubling | 17.60 |
Surendranagar-Rajkot Doubling (116.17 Km) | Chamaraj – Ramparada | February 2020 | Doubling | 23.86 |
Palanpur-Samakhiyali Doubling | Bhildi-Diyodar | May 2019 | Doubling | 26.24 |
Palanpur-Samakhiyali Doubling | Kidiyanagar-Samakhiali | June 2019 | Doubling | 33.59 |